Project Overview Traffic Transportation & Parking Improvements
This project consists of installing dual left turn lanes on North Dean Road at its intersection with East University Drive to accommodate westbound and eastbound turn movements. Removal of the existing traffic signal and installation of a new 4-pole/mast arm signal is also included in this project. The roadways will be resurfaced entirely within the construction limits. The project is part of the City of Auburn's Comprehensive City-Wide Traffic Study.
Please note that project completion dates are subject to change based on weather and other conditions. Project anticipated finish dates may not coincide with actual day of opening.
North Dean Road, East University Drive traffic signal change over expected Feb. 5
Status
- Design
- Bid Advertisement
- Contracts
- Construction
80%
The contractor completed the switch from the old signal poles to the new signal poles. The contractor is working on an updated schedule for completion of the intersection.
Photos




Timeline
Close Out Finishes
May 7, 2025
Close Out Starts
Apr 8, 2025
Construction Finishes
Apr 7, 2025
Construction Starts
Jun 20, 2024
Contracts Finishes
Jun 19, 2024
City Council / AWWB Starts
May 21, 2024
Contracts Starts
May 21, 2024
Bid Opening Starts
May 7, 2024
Bid Advertisement Finishes
May 7, 2024
Bid Advertisement Starts
Apr 14, 2024
Design Finishes
Jun 30, 2023
Design Starts
Sep 5, 2022